EDF Energy – Swindon

Our Client

EDF Energy provides home and business energy in the UK.

edf
Our service delivery

We were appointed to carry out refurbishment/fit out works for EDF’s Swindon location.

Our schedule of works included:

  • Removal and re-instatement of existing carpets
  • Toilet refurbishment including
    • Ceiling & flooring
    • Duct panels,
    • Cubicles and vanity units
    • Doors
    • Mirrors
    • Decorating
  • Glazed Partitions
  • Folding walls
  • Specialist joinery furniture including wardrobe units
  • Sound baffles for glazed partitions and sliding walls

The programme was scheduled carefully to ensure the deadlines were met and minimal disruptions was caused. This including planning deliveries and setting up a delivery bay to ensure goods were delivered safely and effectively.

Contract details

Client: EDF Energy
Sector: Energy
Value: £680,000
Duration: 8 weeks
Start: June 2015
Completion: August 2015